Hi All,
We are planning to implement high availability for Genesys T server.The switch are using is Avaya.The current configuration is we have CTI link on Avaya switch and the T server is communicating with Avaya using this link.
If we want to put one more T server in high availability mode.what is the configuration required on Avaya side to take over the secondery T server in case of primary fails without any manual configuration change.
Kindly reply
-
Hi
You would need to setup and new CTI Link to the AVAYA (second C-Lan Card) and program your vectors to use 2 adjunct steps.
Regards