Title: Question regarding OCS option record_processed
Post by: Ansh on August 15, 2013, 04:25:16 PM
Hi Everyone,

I just need to know if OCS option record_processed is dynamic or no? We are using version 7.2 of OCS and proposing to customer to change this option to False.
Can any of you please verify? I am not able to find this on any of the Genesys docs.
Also if you are aware of the risks involved in change this option to False?

Thanks and regards,
Anshul
Title: Re: Question regarding OCS option record_processed
Post by: cavagnaro on August 15, 2013, 11:30:13 PM
If the parameter doesn't say "DYNAMIC" then it is not
Title: Re: Question regarding OCS option record_processed
Post by: Ansh on August 17, 2013, 12:29:24 PM
Thanks Cav, the problem is that on Genesys site it says 'dynamic' but in the documents there is no information at all. I am sure its dynamic in 8x but we have a very old 7.2 OCS in our environment (We are upgrading to 8.1 by end of this year). Because we don't have a test setup in pre-prod we have to directly implement this in Prod, so I was curious to know if we will have to restart OCS or no.
I guess I will have to restart in case I don't get any information.
Title: Re: Question regarding OCS option record_processed
Post by: cavagnaro on August 17, 2013, 07:32:09 PM
What you mean no information at all??

[quote]
record_processed
Type: Optional
Default Value: true
Valid Value(s): yes/true or no/false
Changes Take Effect: Immediately
[/quote]

So...as stated immediatly. No need to restart
Title: Re: Question regarding OCS option record_processed
Post by: Timur Karimov on August 22, 2013, 06:08:34 PM
Cav,
you mess the OCS version. In doc for 7.2 options description does not contain any additional comments like in later doc version
WBR
Title: Re: Question regarding OCS option record_processed
Post by: cavagnaro on August 23, 2013, 02:47:09 PM
:o I did! Sorry! This was from 7.6  :-X
Title: Re: Question regarding OCS option record_processed
Post by: Ansh on October 14, 2013, 03:14:59 PM
Hello Everyone,

It does require restart of OCS on 7.2 version according to Genesys tech support.
However, when I changed the option I could see it updated immediately in OCS logs without having to restart.

I anyways restarted OCS to be sure.

Thanks,
Ansh